Summary
Use Coe–Clevenger or Talmage–Fitch batch settling data to calculate area, check installed capacity and balance water at a specified underflow concentration.
Ribbon Flowsheet → Dewatering → Thickeners
Model key DPSIM.Dewatering.SettlingTestThickener
Ports
| Port | Direction | Meaning |
|---|---|---|
| Feed | Input | Slurry with a dry-solids rate and component density. |
| Underflow | Output | All feed solids and water at the specified concentration. |
| Overflow | Output | Clear water remaining after the underflow allocation. |
Configuration in DPSIM
- Set the method, underflow target, scale factor and installed area if checking capacity in Operating Basis.
- Enter two-column test data in Test Data. For Coe–Clevenger use initial test concentration and initial zone-settling velocity. For Talmage–Fitch, enter initial height and concentration and choose how the target time will be calculated.
- In Review, check the controlling concentration or height and time construction. Apply and run to record the result in Calculated Parameters.
- Compare underflow concentration and water balance with the design basis, then check required area and the installed-capacity margin.

Parameters and units
| Input | Units or options | Initial value or basis | Use |
|---|---|---|---|
| Test method | Coe–Clevenger or Talmage–Fitch | Coe–Clevenger | Choose the method supported by the available settling data. |
| Operating mode and installed active area | Sizing or capacity check, m² | Size required area, 30 m² for check | Use installed area for an operating-capacity result. |
| Underflow target Cᵤ | kg dry solids/m³ of underflow slurry | 300 | Use a slurry-volume concentration basis. |
| Area scale-up factor f | Positive dimensionless value | 1 | Use 1 for laboratory basis. Document any engineering scale factor. |
| Coe–Clevenger pairs | Initial concentration kg/m³ and initial velocity m/h | Measured series | Enter increasing concentrations greater than zero and below Cᵤ, with positive velocities. |
| Talmage–Fitch initial geometry | H₀ in m and C₀ in kg/m³ | Measured values | Set initial height and concentration for the batch test. |
| Talmage–Fitch time basis | Evaluated time, Critical tangent or Pre-compression crossing | Evaluated time | Provide the associated elapsed time or curve and the selected onset. |
| Critical tangent data | Anchor time in s, height in m and downward velocity in m/h | Measured or interpreted | Use positive downward speed on the stated unit basis. |
Calculation and assumptions
Coe–Clevenger
For each measured initial concentration C and initial zone velocity v, calculate the unit settling area. Convert velocity from m/h to m/s and calculate the maximum of the sampled areas. A single point provides a preliminary area.
Uₐ = (1/C − 1/Cᵤ) / v
Talmage–Fitch
Compute the underflow-equivalent height Hᵤ. The evaluated-time branch uses your documented test time. Critical tangent projects the chosen compression-onset anchor to Hᵤ. Pre-compression crossing interpolates the measured curve within the segment up to the selected onset. A measured curve starts at time zero and H₀, with increasing times and non-increasing heights.
Hᵤ = H₀ C₀/Cᵤ tᵤ = t_c + (H_c − Hᵤ)/(v/3600) for critical tangent, v in m/h Uₐ = tᵤ/(C₀ H₀)
Area and capacity
With f the area scale-up factor and S dry solids in kg/s, required area is fUₐS. The model converts the unit area to m² per t/d and m² per t/h for reporting. To obtain the installed solids capacity in kg/s, divide installed area by scaled unit area.
A_required = f Uₐ S S_capacity = A_installed/(f Uₐ)
Slurry and water balance
The entered Cᵤ fixes underflow volume from the dry solids rate. Subtract dry solid volume from that slurry volume to calculate underflow water, using the feed solids density and a water density of 1,000 kg/m³. Clear overflow receives the remaining feed water. A target that requires more water than the feed is rejected.
Application
Use tests representative of the ore, dilution, solids conditioning and flocculant. Consider which concentrations control the area or which section of the settling curve supports the target time. Torque, bed depth and overflow contamination require separate assessment.
Calculated results
| Result | Units or basis | How to interpret it |
|---|---|---|
| Controlling measured point or target height and time | kg/m³, m/h, m and s | Reproduce the selected laboratory calculation before applying the scale factor. |
| Unscaled and design unit area | m²·s/kg, m² per t/d and m² per t/h | Compare using the denominator reported by the model. |
| Required area, installed capacity and margin | m² and t/h | A negative capacity margin indicates overload while the full feed balance is retained. |
| Feed and underflow volume, clear overflow and underflow solids | m³/h and % w/w | Review the water balance and compare the concentration basis with the target Cᵤ. |
Worked verification example
Use 24 dry t/h, 232 t/h water, feed solids density 3,000 kg/m³, Cᵤ = 300 kg/m³ and area factor 1. For Talmage–Fitch choose H₀ = 0.60 m and C₀ = 100 kg/m³, anchor at 300 s and 0.35 m, and downward tangent speed 1.8 m/h. For Coe–Clevenger use 100 kg/m³ at 0.20 m/h and 200 kg/m³ at 0.04 m/h.
| Check | Calculation or basis | Expected value |
|---|---|---|
| Underflow and clear overflow | Underflow = 24,000/300. Its dry volume is 8 m³/h. | 80 m³/h underflow, 72 t/h underflow water and 160 t/h clear overflow |
| Talmage–Fitch target height and time | Project the selected tangent | 0.20 m and 600 s |
| Talmage–Fitch unit and total area | 600/(100 × 0.60) and × 24/3.6 | 10 m²·s/kg and 66.67 m² |
| Coe–Clevenger unit areas | First and second tests in the same mass-rate basis | 1.388889 and 1.736111 m² per t/d |
| Coe–Clevenger controlling area | 200 kg/m³ point controls, at 576 dry t/d | 1,000 m² |
Diagnostics and calibration
| What you see | What to check |
|---|---|
| Computed target time rejected | Check initial height and target concentration. Confirm that the crossing lies in the selected pre-compression segment or use a documented critical tangent. |
| Area is sensitive to the concentration series | Test additional concentrations around the observed maximum. A one-point test leaves the peak uncertain. |
| Water needed for underflow exceeds feed water | Check solids density and concentration units. Confirm the requested underflow concentration is compatible with the feed. |